ARTICLE
IV - STORMWATER MANAGEMENT
SECTION 401. GENERAL PROCEDURES FOR WATER QUALITY AND QUANTITY CONTROL
SECTION 402. STORMWATER MANAGEMENT DISTRICTS
SECTION 403. STORMWATER MANAGEMENT DISTRICT IMPLEMENTATION PROVISIONS
SECTION
404. WATER QUALITY REQUIREMENTS
SECTION 405. CALCULATION METHODOLOGY
SECTION
406. DESIGN CRITERIA FOR STORMWATER
MANAGEMENT FACILITIES
SECTION 407. EROSION AND SEDIMENTATION REQUIREMENTS
SECTION
401. GENERAL PROCEDURES FOR WATER
QUALITY AND QUANTITY CONTROL
A.
All regulated activities in the Township which do not fall under the
exemption criterion shown in Ordinance Section 302 shall submit a drainage plan
consistent with the Chester Creek Stormwater Management Plan to the Township for
review. This criterion shall apply
to the total proposed development even if development is to take place in
stages. Impervious cover shall
include, but not be limited to, any roof, parking, or driveway areas and any new
streets and sidewalks. Any areas
designed to initially be gravel or crushed stone shall be assumed to be
impervious.
B.
Drainage plans shall be prepared in accordance with the provisions
contained in this article. The
process for implementing these provisions is illustrated in Figure 4-1, Water
Quality and Quantity Control Drainage Plan Preparation Procedures.
C.
The Chester Creek Stormwater Management Plan requires water quality and
water quantity controls as illustrated on the flow chart shown in Figure
4-1 and detailed in Section 404. The
flow chart illustrates a three-step hierarchical process:
Step 1 - Infiltration, Step 2 - Extended detention, and Step 3 -
Implementation of additional design controls.
Applicants must evaluate the outcome of each step before proceeding to
the next. In addition,
riparian buffers are required where applicable, in accordance with Section
404.A.2.
D.
Applicants are highly encouraged to meet the post-development peak
discharge control criteria indicated in Sections 402 and 403 through use of BMPs
and innovative site designs that minimize the amount of new impervious surface.
SECTION 402. STORMWATER MANAGEMENT DISTRICTS
A.
The Chester Creek watershed is divided into districts that represent
three (3) levels of stormwater management.
The boundaries of the stormwater management districts are shown on an
official release rate map, included
as part of the Chester Creek Stormwater Management Plan (see Plate 6, Release Rate Map). A
copy of the official release rate map at a reduced scale is included as Plate
1 in Appendix A of this Ordinance. This
map is for reference only. The
exact location of the stormwater management district boundaries as they apply to
a given development site must be determined by mapping the boundaries using the
two-foot topographic contours (or the most accurate data required) provided as
part of the drainage plan.
B.
All other areas of the municipality not in the Chester Creek watershed
shall be required to utilize a 100% release rate when developing stormwater
controls in conformance with
Section 403 of this ordinance.
WATER
QUALITY and QUANTITY CONTROL
DRAINAGE PLAN PREPARATION PROCEDURE
SECTION
403. STORMWATER
MANAGEMENT DISTRICT
IMPLEMENTATION PROVISIONS (Performance Standards)
A.
General - Post-development rates of runoff from any regulated activity
shall not exceed the peak release rates of runoff prior to development for the
design storms specified on the official stormwater management release rate map,
Ordinance Appendix A, and Section 402 of the Ordinance [,whichever
applies].
B.
Standards for managing runoff for new development from each subarea in
the Chester Creek watershed for the 2-, 5-, 10-, 25-, 50-, and 100-year design
storms are shown in Table 403-1. Development
sites located in each of the districts must control post-development peak runoff
rates to the specified percentage of pre-development peak runoff rates for the
design storms as shown in the table.
|
TABLE
403-1 CONTROL
CRITERIA FOR STORMWATER
MANAGEMENT DISTRICTS |
|
|
DISTRICT |
CONTROL
CRITERIA |
|
100% |
Post-development
peak discharge for all design storms must be no greater than
pre-development peak discharges. |
|
75% |
Post-development
peak discharge for all design storms must be no greater than
seventy-five (75) percent of the pre-development peak discharges. |
|
50% |
Post-development
peak discharge for all design storms must be no greater than fifty (50)
percent of the pre-development peak discharges. |
SOURCE: Gannett Fleming, 2001
All
other areas of the Township shall utilize a 100% release rate for the purpose of
implementation of this Ordinance.
C.
Redevelopment projects shall meet peak discharge requirements based on
the adjusted runoff control number (RCN) or “C”
value illustrated by Figure B-3 in Appendix
B.
D. Sites Located in More than One District - for a proposed
development site located within two or more release category subareas, the peak
discharge rate from any subarea shall be the pre-development peak discharge for
each subarea multiplied by the applicable release rate.
The calculated peak discharges shall apply regardless of whether the
grading plan changes the drainage area by subarea.
E. Off-site Areas - Off-site areas that drain through a proposed
development site are not subject to release rate criteria when determining
allowable peak runoff rates. However,
on-site drainage facilities shall be designed to safely convey off-site flows
through the development site.
F. Site Areas - Where the site area to be impacted by a
proposed development activity differs significantly from the total site area, as
determined by the municipal Engineer, only the proposed development area and
areas contributory to the proposed stormwater management facilities shall be
subject to the release rate criteria.
SECTION 404. WATER QUALITY REQUIREMENTS
A.
In addition to the performance standards and design criteria requirements
of Sections 402 and 403 and Sections 405 through 407 of this Ordinance, the
applicant shall comply with the following water quality requirements unless
otherwise exempted by provisions of this Ordinance.
1.
The applicant shall first provide infiltration facilities in areas where soils
are suitable for infiltration and shall direct the runoff from impervious
surfaces into those infiltration facilities.
The volume of storage to be provided shall be no less than the net
increase in runoff from the 2-year storm event, or one (1) inch of runoff from
the total area draining to the infiltration facility, whichever is greater.
2.
If a perennial or intermittent stream passes through the site, the applicant
shall create a riparian buffer extending a minimum of fifty
(50) feet to either side of the top of the bank of the channel.
The buffer area shall be maintained with appropriate native vegetation
(see list of technical references in Appendix C of this Ordinance).
If the applicable rear or side yard setback is less than fifty
(50) feet, the buffer width may be reduced to twenty-five (25)
percent of the setback to a minimum of ten (10) feet.
If an existing buffer is legally prescribed (e.g., deed covenant,
easement, etc.) and it exceeds the requirement of this Ordinance, the existing
buffer shall be maintained.
3.
Detain the 2-year, 24-hour design
storm runoff based on using the SCS Type II distribution.
Provisions shall be made so that the detained runoff takes a minimum of
twenty-four (24) hours to drain from the facility from a point where the maximum
volume of water is captured (i.e., the maximum water surface elevation is
achieved in the facility). Release
of water can begin at the start of the storm (i.e., the invert of the water
quality orifice is at the invert of the facility).
The design of the facility shall consider and minimize the chances of
clogging and sedimentation potential. The
applicant may also utilize infiltration facilities in lieu of extended
detention. The volume of
infiltration provided for the contributing area may be deducted from the volume
requirement for extended detention.
B.
The applicant shall submit designs for water quality facilities to the
Township Engineer for review and approval.
Such designs may achieve the water quality objectives through a
combination of BMPs.
C.
In selecting the appropriate BMPs or combinations thereof, the applicant
shall consider the following:
1.
Total contributing area
2.
Permeability and infiltration rate of the site soils
3.
Slope and depth to bedrock
4.
Seasonal high water table
5.
Proximity to building foundations and well heads
6.
Erodibility of soils
7.
Land availability and configuration of the topography
8.
Consistency with approved watershed and stormwater management plans or
regulations.
D.
The following additional factors should be considered when evaluating the
suitability of BMPs used to control water quality at a given development site:
1.
Peak discharge and required volume control
2.
Streambank erosion
3.
Efficiency of the BMPs to mitigate potential water quality problems
4.
The volume of runoff that will be effectively treated
5.
The nature of the pollutant being removed
6.
Maintenance requirements
7.
Creation/protection of aquatic and wildlife habitat
8.
Recreational value
9.
Enhancement of aesthetic and property value
SECTION 405. CALCULATION METHODOLOGY
A.
Any stormwater runoff calculations involving drainage areas greater than
two hundred (200) acres, including on-and off-site areas, shall use a generally
accepted calculation technique that is based on the NRCS soil-cover complex
method. Table 405-1 summarizes
acceptable computation methods. It
is assumed that all methods will be selected by the design professional based on
the individual limitations and suitability of each method for a particular site.
|
TABLE
405-1
ACCEPTABLE COMPUTATION METHODOLOGIES FOR STORMWATER
MANAGEMENT PLANS |
||
|
METHOD |
METHOD
DEVELOPED BY |
APPLICABILITY |
|
TR-20
or commercial package based on TR-20 |
USDA
- NRCS |
When
use of full model is desirable or necessary |
|
Tr-55
or commercial package based on TR-55 |
USDA
- NRCS |
Applicable
for plans within the model’s limitations |
|
HEC-HMS |
U.S.
Army Corps of Eng. |
When
use of full model is desirable or necessary |
|
PSRM |
Penn
State Univ. |
When
use of full model is desirable or necessary |
|
Rational
Method or commercial package based on Rational Method* |
Emil
Kuiching (1889) |
For
sites with a total contributing drainage area of less than one hundred
(100) acres |
|
Other
methods |
Various |
As
approved by the Township Engineer |
SOURCE:
Gannett Fleming, 2001
B.
All calculations consistent with this Ordinance using the soil-cover
complex method shall use the appropriate design rainfall depths for the various
return period storms presented in Table B-1 in Appendix B of this Ordinance.
If a hydrologic computer model such as PSRM or HEC-1 is used for
stormwater runoff calculations, then the duration of rainfall shall be
twenty-four (24) hours. The NRCS “S”
curve shown in Figure B-1, Appendix B of this Ordinance shall be used for the
rainfall distribution.
C.
For the purposes of pre-development flow rate determination, undeveloped
land shall be considered as “meadow” good condition, type “B”
soils, (RCN = 58, Rational “C”
= 0.12) unless the natural ground cover generates a lower curve number or
Rational “C”
value (i.e., forest). If a proposed
development meets the definition of redevelopment as defined in Article II of
this Ordinance, the applicant may adjust the pre-development RCN or “C”
value based on the curves presented in Figure B-3.
D.
All calculations using the Rational Method shall use rainfall intensities
consistent with appropriate times of concentration for overland flow and return
periods from the design storm curves from PA Department of Transportation Design
Rainfall Curves (1986) (Figure B-2). Times
of concentration for overland flow shall be calculated using the methodology
presented in Chapter 10 of Pa Department of Transportation Design Manual Part 2. Times of concentration for channel and pipe flow shall be
computed using Manning’s Equation.
E. RCNs for both existing and proposed conditions to be used in the soil-cover complex method shall be obtained from Table B-2 in Appendix B of this Ordinance.
F.
Runoff coefficients (C) for both existing and proposed conditions for use
in the Rational Method shall be obtained from Table B-3 in Appendix B of this
Ordinance.
G.
Runoff characteristics of off-site areas that drain through a proposed
development shall be based on actual existing conditions, not RCN=58 or C=0.12,
and shall be assumed to not have any controls implemented on future development
(i.e., no release rate restrictions).
H.
Where uniform flow is anticipated, the Manning equation shall be used for
hydraulic
computations and to determine the capacity of open channels, pipes, and
storm sewers. Values for Manning’s roughness coefficient (n) shall be
consistent with Table B-4 in Appendix B of the Ordinance.
I.
Outlet structures for stormwater management facilities shall be designed
to meet the performance standards of this Ordinance using any generally accepted
hydraulic analysis technique or method. Acceptable
methods are presented in Handbook of
Hydraulics, by King and Brater (McGraw Hill).
In addition, application of computer programs such as HY-8 (Federal
Highway Administration) or FlowMaster (Haestad Methods) will also be accepted.
J.
The design of any stormwater detention facilities intended to meet the
performance standards of this Ordinance shall be verified by routing the design storm
hydrograph through these facilities using the Storage-Indication Method.
For drainage areas greater than twenty (20) acres in size, the design
storm hydrograph shall be computed using a calculation method that produces a
full hydrograph. The Municipality
may approve the use of any generally accepted full hydrograph approximation
technique that uses a total runoff volume that is consistent with the volume
from a method that produces a full hydrograph.
K. The Township has the authority to require that computed existing runoff rates be reconciled with field observations and conditions. If the designer can substantiate through actual physical calibration that more appropriate runoff and time-of-concentration values should be utilized at a particular site, then appropriate variations may be made upon review and recommendation of the Township Engineer. Calibration shall require detailed gauge and rainfall data for the particular site in question.
SECTION
406. DESIGN CRITERIA FOR STORMWATER
MANAGEMENT FACILITIES
A.
Any stormwater management facility (i.e., detention basin) designed to
store runoff and requiring a berm or earthen embankment required or regulated by
this Ordinance shall be designed to provide an emergency spillway to handle flow
up to and including the 100-year post-development conditions.
The height of the embankment must be set so as to provide a minimum two
(2.0) feet of freeboard above the maximum pool elevation computed when the
facility functions for the 100-year post-development inflow.
Should any stormwater management facility require a dam safety permit
under DEP Chapter 105, the facility shall be designed in accordance with Chapter
105 and meet the regulations of Chapter 105 concerning dam safety which may be
required to pass storms larger than the 100-year event.
B.
Any facilities that constitute water obstructions (e.g., culverts,
bridges, outfalls, or stream enclosures) and any work involving wetlands as
directed in DEP Chapter 105 regulations (as amended or replaced from time to
time by DEP) shall be designed in accordance with Chapter 105 and will require a
permit from DEP. Any other drainage
conveyance facility that does not fall under Chapter 105 regulations shall be
designed to convey, without damage to the drainage structure or roadway, runoff
from a minimum 25-year design storm. The Township may require design based on a
larger storm event. Open
channels shall be designed with a minimum of one (1.0) foot of freeboard.
Any facility that constitutes a dam as defined in DEP Chapter 105
regulations may require a permit under dam safety regulations.
Any facility located within a PennDOT right-of-way must meet PennDOT
minimum design standards and permit submission requirements.
If the primary drainage facilities do not have capacity for future flows,
then a safe drainage path must be provided to convey up to the 100-year design
storm (without impacting structures).
C.
Storm sewers must be able to convey post-development runoff from a
minimum 25- year design storm without surcharging inlets.
D. Adequate erosion protection shall be provided along all open channels and at all points of discharge.
E.
The design of all stormwater management facilities shall incorporate
sound engineering principles and practices.
The Township shall reserve the right to disapprove any design that would
result in the occurrence or continuation of an adverse hydrologic or hydraulic
condition within the watershed.
F.
Stormwater drainage systems shall be provided in order to permit
unimpeded flow along natural watercourses, except as modified by stormwater
management facilities or open channels consistent with this Ordinance.
G.
The existing points of concentrated drainage that discharge onto adjacent
property shall not be altered without permission of the adjacent property
owner(s) and shall be subject to any applicable discharge criteria specified in
this Ordinance.
H.
Areas of existing diffused drainage discharge shall be subject to any
applicable discharge criteria in the general direction of existing discharge,
whether proposed to be concentrated or maintained as diffused drainage areas,
except as otherwise provided by this Ordinance.
If diffused flow is proposed to be concentrated and discharged onto
adjacent property, the applicant must document to the Township in accordance
with Section 405 that adequate downstream conveyance exists to safely transport
the concentrated discharge, or the applicant must obtain drainage easements from
affected downstream property owners and provide the facilities to safely convey
the flow.
I.
Downstream Hydraulic Capacity Analysis - Any downstream capacity
hydraulic analysis conducted in
accordance with this Ordinance shall use the following criteria for determining
adequacy for accepting increased peak flow rates:
1.
Natural or man-made channels or swales must be able to convey the
increased runoff associated with a 2-year return period event within their banks
at velocities consistent with protection of the channels from erosion.
Acceptable velocities shall be based upon criteria included in the DEP Erosion
and Sediment Pollution Control Program Manual.
2.
Natural or man-made channels or swales must be able to convey the
increased 25-year return period runoff without creating any hazard to persons or
property.
3.
Culverts, bridges, storm sewers, or any other facilities which must pass
or convey flows from the tributary area must be designed in accordance with DEP,
Chapter 105 regulations (if applicable) and, at a minimum, pass the increased
25-year return period runoff.
J.
Where a development site is traversed by watercourses, riparian buffers
shall be provided conforming to the line of such watercourses. The width of the buffers shall be determined as set forth in
Section 404.A.2. Excavating,
placing of fill, building structures, or making any alterations that may
adversely affect the flow of stormwater within any portion of the riparian
buffer shall be prohibited unless the proposed work is associated with a
regulated wetlands mitigation program. The
buffer must be defined through a deed covenant.
K.
When it can be shown that, due to topographic conditions, natural
drainageways on the site cannot adequately provide for drainage, open channels
may be constructed conforming substantially to the line and grade of such
natural drainageways. Work within
natural drainageways shall be subject to approval by DEP through the Joint
Permit Application process, or, where deemed appropriate by DEP, through the
General Permit process.
L.
Any stormwater management facilities regulated by this Ordinance that
would be located in or adjacent to waters of the Commonwealth or wetlands shall
be subject to approval by DEP through the Joint Permit Application process, or,
where deemed appropriate by DEP, the General Permit process. When there is a question as to whether wetlands may be
involved, it is the responsibility of the applicant or his agent to show that
the land in question cannot be classified as wetlands; otherwise, approval to
work in the area must be obtained from DEP.
M.
Any stormwater management facilities regulated by this Ordinance that
would be located on state highway rights-of-way shall be subject to approval by
PennDOT.
N.
Minimization of impervious surfaces and infiltration of runoff through
seepage beds, infiltration trenches, etc. are required, where soil conditions
permit, to reduce the size or eliminate the need for detention facilities.
O. In order to promote overland flow and infiltration/percolation of stormwater, roof drains must discharge into an accepted BMP providing infiltration and filtering of the stormwater.
SECTION 407. EROSION AND SEDIMENTATION REQUIREMENTS
A.
Whenever the vegetation and topography are to be disturbed, such activity
must be in conformance with Chapter 102, Title 25, Rules and Regulations, Part
I, Commonwealth of Pennsylvania, DEP, Subpart C, protection of Natural
Resources, Article II, Water Resources, Chapter 102, “Erosion Control,” and
in accordance with the Delaware County Conservation District and the standards
and specifications of the Township.
B.
Additional erosion and sedimentation control design standards and
criteria that must be applied where infiltration BMPs are proposed include the
following:
1.
Areas proposed for infiltration BMPs shall be protected from
sedimentation and compaction during the construction phase to maintain their
maximum infiltration capacity.
2.
In order to ensure compliance with Chapter 102, the timing of the
installation and operation of the infiltration BMP shall be at the discretion of
the Township Engineer.